Use Of Funds
The project is planned to cover an area of 100 mu, with a total construction area of 11 20000 square meters. It mainly constructs the cell plant, finished product warehouse, waste warehouse and soaking pool, fire station building and monitoring room, sewage treatment station, power station, electrolyte warehouse, NMP pump room, NMP Tank farm, raw material warehouse, safety laboratory, waste treatment station, pilot plant, R&D testing, accident pool, initial rainwater collection pool, corridor, cell plant, electrolyte warehouse complex building, gatekeeper. Introduce battery production line and produce sodium ion battery production line, including raw material preparation, module packaging and other links.
Return Analysis
It is estimated that the annual output value is about 2.5 billion yuan, driving 2000 jobs.
Contact Information
Contact: Zhu Qing
Phone: 13991121199